Tempus at Parc Y Coleg - Construction Snapshot: May 2026


The doors are open
Last month marked a significant moment for Tempus, with the opening of the Sales Suite drawing strong attendance from prospective buyers. Interest across the weekend was considerable, with visitors exploring the suite and getting their first look at the bespoke specification planned for the apartments. The response reflects the appetite for a development of this calibre in Caerleon.

The Tempus At Parc y Coleg sales board in position on Lodge Road, marking the opening of the development to prospective buyers.
Inside the marketing Suite
The Marketing Suite itself demonstrates the quality of finish planned across the development, giving visitors a tangible sense of what to expect from the completed apartments. Set within the restored caretaker's house, the suite features period windows and a considered interior, providing an appropriate first impression of a conversion scheme of this character.

The completed Marketing Suite open to visitors, with interiors reflecting the bespoke specification planned across the Tempus apartments.
Main building advancing
Inside the principal Grade II listed building, drylining of the internal walls is now underway, marking the transition from enabling and clearance works into active fit-out. The floor plates, stripped back and cleared in earlier phases, are now beginning to take on the layout of the future apartments. The scale and character of the building, with its generous ceiling heights and original features, remains fully apparent as the work progresses.

The Tempus site from above, with the four new-build houses and landscaped grounds visible alongside the main listed building.
Plant room and M&E under way
In the basement, mechanical and electrical installation is progressing in the plant room, with main boilers and water tanks now commenced. This shared infrastructure is a key milestone in the building's conversion, underpinning the services that will run throughout the completed apartments. With M&E active at basement level and drylining progressing above, the building is moving through its phases in a logical sequence.
Contact Us
Fill out the form below and we will contact you soon.


