The content of the financial promotions on this website has not been approved by an authorised person within the meaning of the Financial Services and Markets Act 2000. Reliance on these promotions for the purpose of engaging in investment activity may expose an individual to a significant risk of losing all of the property or assets invested.

Project UpdateMarket Quay
September 25, 2025 | 5 min read

Market Quay - Construction Snapshot: September 2025

August saw continued momentum at Market Quay, with works advancing across groundworks and structural preparation. Façade retention is progressing on schedule, while reinforced concrete works and waterproofing have taken shape across key areas of the site.

By Frank Dost
Share on:

Groundworks and structural activity progress

The crane is now in operation, supporting reinforced concrete works to the bank and Plots 9 to 13. Waterproof membranes and steel reinforcement have been installed to several sections, with concrete pours underway. The sea defence wall is also well underway, with shuttering and casting taking place. The photos below show the front façade now fully retained with steel supports, allowing safe demolition of the old concrete roof and internal structures behind it.

The original façade is held in place by steel supports, preserving its character while construction progresses behind it.

Looking ahead to the new structure

Upcoming phases will focus on forming blockwork cores, installing block and beam floors, and commencing steel framing to the ground floor. Scaffold is being extended to support roof removal at the bank, and internal layout works are progressing in tandem. Procurement is running on schedule, with key orders placed for windows, roof timbers, and joists. The site continues to evolve rapidly, setting strong foundations for the build to come.