Hensol Grove - Construction Snapshot: October 2025
Momentum continues at Hensol Grove as early construction milestones begin to take shape across the Mews homes. The front of site is beginning to establish a clear layout, supported by visible structural progress and the ongoing coordination of key groundwork.

Groundworks and Structural Elements Moving at Pace
Plot 10 has now reached full height and is prepared to receive its roof structure. Elsewhere, foundations across all Mews plots have been completed, and the reinforced concrete retaining wall is in place. Waterproofing of the wall is nearly finished, with backfilling underway. Internally, drainage works are progressing across Plots 1 to 3, ahead of slab installation.

Foundation & Retaining Walls
Externally, work has commenced on the main drain runs, helping prepare the wider site for further construction and services installation. Slab installation for the early plots is expected to follow, allowing continued progress across the Mews.

Catch Up on the Latest Site Footage