Canynge Place - Construction Snapshot: March 2026


Fit-Out Progressing Across Both Wings
The west wing is furthest ahead, with second fix underway across a number of units. Kitchen installations, tiling, sanitary ware and flooring are all actively in progress. The east wing is following in sequence, with second fix joinery now started and skim being completed throughout. In the basement, boarding is also underway.

Inside the east wing second fix joinery is underway as Somerset House continues its transformation from 1960s office building to 35 contemporary Clifton apartments.
Exterior Works Advancing
Cladding has recommenced across the building, with the entrance canopy structure now underway. The remaining window cills are being sprayed as the external envelope is brought progressively closer to completion.
Show Home Now Open
The Canynge Place show home opened in February, giving buyers the opportunity to see the quality of the specification first-hand. Viewings are available Tuesday to Thursday, 8.30am to 5pm, with appointments outside those hours also available.

Canynge Place show home interiors showing the kitchen, living area, bedroom and bathroom of a two-bedroom apartment.